Project case study
Boeing Reserve.
Cricket-net enclosure renewal, built from demolition through to the finished synthetic surface.
The brief
A solid platform for cricket.
RMS delivered the demolition, ground preparation, drainage, concrete and fencing interface for a new cricket-net enclosure. The work brought the civil and sports-surface elements together in one coordinated construction sequence.
ClientMoonee Valley City Council
Groundworks400mm strip, cut and fill, and compacted pavement layers
Facility finishConcrete enclosure, retaining walls and 9mm synthetic cricket grass
400mmStrip depth
150mmType A capping
150mmClass 2 layer
140mmConcrete slab
Similar project?
Bring RMS
the brief.
RMS coordinates the civil works and sports-facility interfaces so the finished site is ready for its intended use.
Project enquiriesinfo@rmsgroundworks.comOffice(03) 9469 3375